Complete revamping and repowering of the existing plant
Brescia
The project carried out at the S.A. Eredi Gnutti Metalli S.p.A. plant in Brescia involved the complete revamping and repowering of the photovoltaic system, which began operating in 2011, with the goal of restoring its performance following the weather events of 2023 and significantly increasing its efficiency.
The project increased the installed capacity from 4,839 kWp to 6,687 kWp, with an expected annual output of 6,809 MWh (of which 1,847 kWp is currently awaiting grid connection authorization)
The site has also been equipped with a 3,946 kWp ground-mounted photovoltaic system, capable of generating 5,053 MWh per year.
Overall, the project strengthens the site’s energy self-sufficiency and reaffirms the company’s commitment to sustainability and the decarbonization of industrial processes.
The project required a highly specialized approach, as it involved working on a large-scale facility that was already in operation while ensuring operational continuity.
Further complications arose from:
*Of which 1,847 kWp is in the process of obtaining a connection permit